Oh the joys of major construction projects! We were informed Monday that the crane we scheduled for 9/22/15, after being unavailable for a week (yet another thing to push us off schedule), is having mechanical problems and has to be repaired. This repair will push back boulder placement for two days, and will push tree placement and planting to next week.
The silver lining in all of this is because of the delays related to contract, permits, product availability, crew availability, architectural review, and repairs, plus super heat, the trees, plants and flowers will have a much more ideal planting time now that it is early Autumn.